UE E&C Ltd on Wednesday announced that its unit, United Engineers (Singapore) Private Limited, was awarded the tender for a $37.7 million sub-contract by Kajima Overseas Asia Pte Ltd.
Under the contract, United Engineers will install air-conditioning and mechanical ventilation at the Singapore University of Technology and Design.
Works on the academic buildings at Somapah Road / Changi South Avenue 1 will take 31 months andis expected to be completed by March 1, 2015.
The group said that the project will not have a material impact on the consolidated net tangible assets per share and consolidated earnings per share of the group for the current financial year ending December 31, 2012.
Under the contract, United Engineers will install air-conditioning and mechanical ventilation at the Singapore University of Technology and Design.
Works on the academic buildings at Somapah Road / Changi South Avenue 1 will take 31 months andis expected to be completed by March 1, 2015.
The group said that the project will not have a material impact on the consolidated net tangible assets per share and consolidated earnings per share of the group for the current financial year ending December 31, 2012.