United Kingdom : Balfour Beatty selected for Gatwick Airports Capital

Published 01 Aug 2016

Balfour Beatty has been selected by Gatwick Airport to deliver a range of projects under its new 1.2 billion capital investment programme, which will deliver expansion in scale and passenger capacity.

The company has been appointed to two frameworks, the Low Complexity Build and Low Complexity Civils Framework, as well as the Medium Complexity Build Framework. It is expected that projects delivered through these frameworks will be procured over the next five years.

In total there were some 127 bidders for the workload, with just 17 successful bids. Balfour Beatty was selected because of its experience in the sector, and its collaborative approach.

Balfour Beatty has a long standing relationship with Gatwick, for which it has delivered in excess of 500 projects, including upgrades to the security lanes, the Pier 11 build, and the 50 million refurbishment of the North Terminal.